The Kaohsiung International Airport runway renovation project includes a 7.5-hour nighttime task.

Yongli is conducting 7.5-hour nighttime construction work at Kaohsiung International Airport daily.

The runway renovation was completed, employing full-section hot-joint paving, patented rapid cooling, and FOD safety control, ensuring timely and high-quality delivery and maintaining normal daytime airport operations.

Project Summary

This project involves the runway renovation of Kaohsiung International Airport.

Yongli needs to complete the project within a timeframe shorter than the ICAO recommended standard.

Complete the removal, overlay, and lighting restoration under constraints.

FOD clearance. Through mature runway construction methods and...

Patented equipment successfully achieves "daily construction, every..."

The task is to "resume operations daily".


  • Project Type: International Airport Runway Reconstruction
  • Construction hours: 23:30–06:50 (limited time during nighttime hours)
  • Technical highlights: Hot-bonded installation, rapid cooling technology
  • Precision planing, expansion joint suppression
  • Results: Completed on schedule and to a high standard, with work resuming promptly every morning.
  • Resumption of flight operations

Inquiry about engineering business

Contact Us